T17 Improvements at South Street & West Street

  • ID: T17
  • Type: Street Improvements
  • Phase: Design

Project Summary

See the Project Map.

The intersection at South Street and West Street is offset. This project will assess and determine the best solutions to improve this intersection and the congestion along both South Street and West Drive. Relocation of utilities may also be required.

Intersection improvements should improve traffic safety and continuous vehicle flow, especially during the school year as Camacho Elementary and Leander Middle School are located just south of this area.

Project Budget

Amended - $765,500 for design and construction (2021)

Initial - $704,940 for design and construction (2019)

Source - General obligation bonds (issued 2018)

Project Updates

  • August 4, 2020 - Design contract amended to $131,697.
  • January 7, 2020 - Design contract amended to $108,343.
  • February 7, 2019 - Design contract of $87,221 awarded to Binkley and Barfield.

Capital Improvement Program (CIP) Oversight

This project is managed under the city's Capital Improvement Program (CIP), a comprehensive planning effort designed to prioritize and coordinate the development of capital projects to meet Leander's public infrastructure needs today and in the future.

Rendering of Intersection at South Street and West Street